Situation

A leading supplier of forgings to Tier I and II aerospace, defense, and automotive companies won a significant contract. As the company ramped up a new production process under the contract, they discovered their outsourcing operations resulted in high costs and compromised quality.

Goal

The company identified process improvements that would lower costs, improve quality, and reduce lead time. The engineering staff specified equipment that would enable them to bring revised operations in-source and reduce travel time and supplier turn time. The process team was tasked with pre-testing different placement scenarios for the equipment and simulating revised operation sequencing.

Objectives

DPA facilitated the kaizen team’s work to understand product flow within the company’s facilities and to external suppliers. They identified risks to product quality, production rates, and other supply chain issues related to logistics and costs. The team, including the plant manager, operators, and a quality engineer, reviewed the drawings and technical capabilities of all ordered equipment. The equipment needed to fit into an area near upstream processes. The objective: to ensure one operator could safely and conveniently manage all operations within the process.

Three people part of the Kaizen team

The Kaizen team at this forging company tested five-floor mockups for a new cell layout that will insource previously outsourced operations.

Tasks

The team analyzed the process from the first forging operation, where the process would start, through to the finish and delivery to the customer. They also sent a representative to the equipment supplier to work with equipment design. They laid out several possible arrangements in full size, using cardboard, pallets, and boxes to represent each piece of equipment. Some layouts fit; others required some compromise in building accessibility, and other options required major infrastructure changes. They also simulated operator motion and activities within the areas to identify operability issues and emergency access.

Findings

The team found that the ideal cell layout would require modifying some equipment. In consultation with the supplier, the company made design changes at a lower cost than the original equipment. They also found that one operator could complete all assigned tasks within their scheduled time. They identified all equipment utility locations so the building could be prepared before arrival, reducing installation time and accelerating process development.

Benefits

Based on their equipment placement and simulation work, the team projects several efficiency improvements for the new operation. In-sourcing of two supplier processes will reduce part travel by 99.8%. Lead times will drop by 60%, and production capacity will increase by 107%. Finally, one operator can perform four operations safely and consistently within his allotted time.